Design of phase 2 parking lot for building A, construction works, architectural supervision, and dismantling of building 37 (phase 1)
Client
VSIA “Paula Stradiņa klīniskā universitātes slimnīca”
Completion year
2024
Total amount
€1 004 619
Project description
Type of construction works – new construction of a parking area, rainwater drainage networks and lighting, CCTV, alarm notification, and electronic communication systems. Provision of design and supervisory services.
Road construction works.
Rainwater drainage networks (451 m)
Electrical supply (external) – lighting (643 m)
0.4 kV electrical supply (627 m)
CCTV, alarm notification (1024 m)
Design – Stage 1
Supervision – Stage 1
Road construction works.
Rainwater drainage networks (451 m)
Electrical supply (external) – lighting (643 m)
0.4 kV electrical supply (627 m)
CCTV, alarm notification (1024 m)
Design – Stage 1
Supervision – Stage 1
Other projects
Improvement of the road surface on Zvanu Street section in Salaspils
Year: 2025
Reconstruction of the state regional road P109 Kandava – Saldus, section 14.033 – 28.637 km
Year: 2024
Reconstruction of the existing container storage area New container storage area in Riga, Kundziņsala, within the Riga Freeport territory
Year: 2025
Reconstruction of the municipal road Klāvi – Zīles (No. 41) in Sesava Parish, Jelgava Municipality
Year: 2024